function XmlHttp() { var xmlhttp; try{xmlhttp = new ActiveXObject("Msxml2.XMLHTTP");} catch(e) { try {xmlhttp = new ActiveXObject("Microsoft.XMLHTTP");} catch (E) {xmlhttp = false;} } if (!xmlhttp && typeof XMLHttpRequest!='undefined') { xmlhttp = new XMLHttpRequest(); } return xmlhttp; } function ajax(param) { if (window.XMLHttpRequest) req = new XmlHttp(); method=(!param.method ? "POST" : param.method.toUpperCase()); if(method=="GET") { send=null; param.url=param.url+"&ajax=true"; } else { send=""; for (var i in param.data) send+= i+"="+param.data[i]+"&"; } req.open(method, param.url, true); if(param.statbox)document.getElementById(param.statbox).innerHTML = ''; req.setRequestHeader("Content-Type", "application/x-www-form-urlencoded"); req.send(send); req.onreadystatechange = function() { if (req.readyState == 4 && req.status == 200) //если ответ положительный { if(param.success)param.success(req.responseText); } } } function proverka(input) { input.value = input.value.replace(/[^\d,]/g, ''); };
В связи с тем, что на месте цеха электросетей по ул. Вознесенской планируется построить филармонию, необходимо было снести не только само здание цеха, но и вынести инженерные коммуникации из зоны строительства нового объекта: снос здания распределительного пункта №2 и перенос КЛ-6кВ и участка тепловой сети.
В течение двух месяцев идут работы по переключению кабельных линий от РП-2 на РП-2Н. Эти работы не приводят к ограничению электроснабжения потребителей.
В декабре было проложено 112 метров нового участка теплотрассы предызолированными трубами от тепловой камеры №618 до здания городской налоговой инспекции. Все строительные работы, начиная от подготовительных, заняли две недели. Чтобы свести к минимуму время останова подачи тепла, демонтаж старой воздушной сети, которая шла через здание электросетей, проведен после строительства новой. Подача тепла была прервана ненадолго: лишь на время переключения потребителя со старой сети на новую.